๐Ÿ“… Realistic UK timeline

Heat Pump Installation Time & Process UK 2026

On-site install is 3-5 days. But the full quote-to-commissioning timeline is 6-10 weeks. Here's the realistic week-by-week schedule, what happens at each step, and how to keep your install on track.

JTJames Thornton, MCS Engineer 1,700 words ยท 8 min read
Quote โ†’ install: 6-10 weeks ยท On-site: 3-5 days
Order early: spring/autumn fastest, winter has 4-6 week installer backlog.
Quick answer: A standard UK heat pump retrofit takes 3-5 working days on-site. The full process from first quote to commissioning runs 6-10 weeks, broken down as: survey (week 1), quote and BUS grant submission (weeks 2-3), equipment order (weeks 3-5), installation week (week 5-7), commissioning (week 7-10). Order in spring or autumn for fastest install โ€” winter has 4-6 week installer backlogs across the UK.

The full UK timeline at a glance

WeekStageWhat happens
1SurveyOn-site visit; heat loss calc; radiator audit; quote prep
2QuoteItemised quote received; contract signed; deposit paid (typically 10-25%)
2-3BUS grantInstaller submits BUS application to MCS; ~10 working days to approve
3-5EquipmentHeat pump and cylinder ordered; 2-4 week lead time for most brands
4-6Pre-workAny new radiators or pipework upgrades (optional, 1-2 day visit before main install)
5-7Main install3-5 days on-site: outdoor unit, cylinder, pipework, electrics, controls
7-10CommissioningFlow temp set, weather compensation programmed, MCS certificate issued, BUS grant deducted from invoice

Week 1 โ€” Survey day

The installer visits for 90 minutes to 3 hours and does:

Most installers issue a written quote within 5-7 days of the survey. If they need longer than 14 days, push back โ€” slow quoters often mean slow installs.

Week 2 โ€” Quote review and contract

A proper quote includes:

If any of these are missing, ask. Don't sign without seeing the heat loss calc.

Weeks 2-3 โ€” BUS grant application

Your installer submits the BUS application to MCS on your behalf. MCS approval typically takes 10 working days (sometimes faster). You don't need to do anything except sign the customer authorisation form your installer provides.

Note: BUS funding is allocated quarterly. If you're applying in Q1 or Q4, watch for budget exhaustion โ€” installers will warn you if your application risks falling into the next quarter.

See: Boiler Upgrade Scheme 2026 Guide

Weeks 3-5 โ€” Equipment order and lead times

Typical UK lead times in 2026:

Winter (Oct-Jan) lead times typically double. Order in March-May for the fastest turnaround.

Weeks 4-6 โ€” Optional pre-work (radiator upgrades)

If your survey found undersized radiators (very common in older homes), the installer may schedule a 1-2 day visit before the main install to swap them. This minimises disruption during the main install week.

Typical scope:

Weeks 5-7 โ€” The main install (3-5 days on-site)

Day 1 โ€” Outdoor unit and base

Day 2 โ€” Indoor cylinder and primary pipework

Day 3 โ€” Electrics and controls

Day 4 โ€” Refrigerant connection, vacuum, gas charge

Day 5 โ€” Commissioning and handover (often 1-2 weeks later)

Weeks 7-10 โ€” Settling-in and follow-up

A good installer will revisit after 4-6 weeks for a free check-up:

This visit is often the single biggest factor in real-world SCOP โ€” first-run settings are typically conservative and can be optimised 0.2-0.4 SCOP higher after data review.

What can slow the timeline

How to keep your install on track

AdSense In-Content Slot

FAQ

How long is the heat pump install actually on-site?
3-5 working days for a standard retrofit. Larger homes or installs with radiator upgrades and electrical work can stretch to 7 days. Commissioning visit is often a separate day 1-2 weeks later.
Will I have heating during the install?
No heating from when the old boiler is removed (Day 2) until first-fire test (Day 3-4). Most installers schedule this in mild weather; some provide temporary electric heaters if needed.
Do I need to be home during the install?
Day 1 (access agreement), Day 5 (handover) โ€” yes. Other days are flexible if you can give a key/access code. Most installers prefer someone home for the gas safe disconnection.
What's the fastest a heat pump can be installed in the UK?
From cold start with Grant Aerona stock and no radiator upgrades: 3-4 weeks total. With Mitsubishi or Vaillant: 5-6 weeks minimum. Anyone promising 1-2 week start dates is likely cutting corners.
When is the best time of year to install?
April-September. Better weather for outdoor work, no installer backlog, no winter heating crunch if anything goes wrong. Avoid Nov-Feb if possible โ€” see our Running Costs guide for season-specific tips.

Related tools

JT

James Thornton

MCS-Certified Heat Pump Engineer โ€” Author

James schedules 30-40 heat pump installs per year. The timelines above are based on his real install records 2022-2025 across the East of England.